Five tips for building a Work Breakdown Structure



A Work Breakdown Structure (WBS) is the best way to understand the detailed work of the project when you have to build a schedule from scratch. It’s used to break the project down into the major phases, deliverables, and work components that will be built by the project. These work components can then be broken down into the activities that are required to build them. The WBS is not the same as the final schedule (which requires sequencing, resources, estimated effort, estimated duration, etc.).
Here are five tips to keep in mind when building your WBS:
#1: Create a WBS dictionary for large projects
Normally you wouldn’t need a WBS dictionary, but if your WBS has hundreds (or thousands) of detailed activities, there may just be too much to keep track of by hand. In this case, it might make sense to place all of the important information in a WBS dictionary. The dictionary helps keep track of all of the summary and detailed activities, including a short description, the WBS numeric identifier (1.1, 1.1.1, 1.1.2, etc.) and the estimated effort. If you enter your WBS dictionary into a specialized tool, the tool can also help to keep track of changes to the WBS as well.
#2: Use the summary activities as milestones
Your WBS should contain both detailed and summary activities. (A summary activity is one that is broken down further; a detailed activity is one that is not broken down further.) Although a schedule usually includes only detailed activities, it makes sense to include the summary activities as milestones (i.e., markers signifying that a deliverable or set of deliverables is complete). A summary activity can be used as a milestone since it would indicate that all of the underlying detailed work has been completed.
#3: Break activities into two or more detailed activities
I’ve seen teams that break one activity in the WBS into only one activity at the next level. In my opinion, this doesn’t make sense because then the detailed activity represents the same work as the prior summary activity. This doesn’t buy you anything.
#4: Make the final detailed activities action oriented
The detailed activities on your WBS (the ones that are not broken down further) are ultimately moved to your schedule. For that reason, it’s easier if the detailed activities in your WBS are action oriented — just as activities in your schedule would be. For example, instead of describing a detailed WBS activity as “meeting,” you should state it as “schedule a weekly meeting.” Instead of having a WBS detailed activity for “Testing Plan,” you should state it instead as “Create Testing Plan.” In this way, the detailed activities can be moved to the schedule with a minimum of wording changes.
#5: Don’t place requirements on the WBS
If you place a deliverable on your WBS, you can break this deliverable down into the activities that are required to create it. You don’t break a deliverable down into the requirements that describe it.Requirements do not belong on a WBS. Only deliverables and activities belong on the WBS.By using these five techniques, you will save you time and rework on your next WBS

Source:http://blogs.techrepublic.com.com/tech-manager/?p=588&tag=rbxccnbtr1

Share this tutorial:
  • Digg
  • del.icio.us
  • Facebook
  • Mixx
  • Google
  • Furl
  • Live
  • PlugIM
  • Reddit
  • Spurl
  • StumbleUpon
  • Technorati
  • TwitThis
  • YahooMyWeb
  • description
  • E-mail this story to a friend!
  • MisterWong
  • BlinkList
  • LinkedIn
  • MySpace
  • Print this article!
  • Yahoo! Buzz

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

About the Author

Adam has written 384 stories on this site.

Related Tutorials & Articles

Consolidate all project management deliverables in the project plan
Many people use the term “project plan” to mean the project schedule (or workplan). However, the project plan is the name given to all of the project management documents used during the project. This term made more sense in years past when you could envision a physical binder that contained hard copies of the project...Read more
What is Project Plan?
The word plan is commonly used in our daily life refers to anything which is decided in advance with the specified timelines in the form of time, day, month and year. Lets take few common example to understand the meaning of Plan •    I am planning to watch this movie on Sunday. •    We are planning for the...Read more
Elements of Project Success
Elements of Project Success A project is defined as a set of tasks having a defined start and end point and specific objectives, requirements, and goals. Clearly, both business continuity and disaster recovery planning qualify as projects under this definition. Following are the elements of project success. -Executive Support -User Involvement -Experienced Project Manager -Clearly Defined Project Objectives -Clearly Defined Project Requirements -Clearly...Read more
What is Project?
Project consist set of tasks which have start and end time, unique in nature and produce a set of deliverables. Project is completed when the goals and objectives of the project are achieved successfully. Project has multiple phases and each phase involves individuals called stakeholders to achieve the milestones and to continue the progress of...Read more
Work Breakdown Structure (WBS)
A work breakdown structure is an extremely valuable and important project management tool. It sets the foundation for the rest of the project planning. Gantt Charts, PERT Charts: What Use Are They? Gantt charts and PERT charts are useful tools for visualising and communicating information about projects, but they have a number of limitations. In addition, the...Read more

Write a Comment

Gravatars are small images that can show your personality. You can get your gravatar for free today!

Copyright © 2010 Sooper Tutorials. All rights reserved. Powered by WordPress.org, Website by ISolution.org.